Planar maglev offers another way to organize production.
The MagiFloater® Planar Motor Systembuilds a working plane from multiple standardized stator modules, on which movers can travel along planned paths within the plane. Products do not all have to pass through exactly the same stations; instead they canchoose different travel paths according to the production task。
Diverting: different products enter different stations
When one machine produces several models, different products may require different processing programs.
After identifying the product task, the system canassign the movers carrying workpieces to the corresponding stations. For example, model A enters the dispensing and inspection stations, model B only undergoes assembly and unloading, while sampled products enter a dedicated inspection area. Multiple products share one working plane while each keeps its own process route.
When changing over, the equipment canadjust tasks, stations and travel pathsto suit new production requirements, reducing the work of rearranging the entire conveying mechanism.
Re-inspection: abnormal products get their own destination
When in-line inspection finds an abnormal product, the common handling methods are stopping the line and removing it manually, or letting it run to the end of the whole process before handling. Both approaches add waiting time or manual intervention.
In a planar maglev system,abnormal products can go directly to the re-inspection area. After passing re-inspection they return to subsequent processes; products confirmed as non-conforming go to a designated unloading position. Normal products keep running, and exception handling can proceed at the same time as the main production flow.
This capability suits scenarios such as vision inspection, electrical performance testing, dimensional inspection and process sampling.
Bypass: a local state change need not block the entire flow
When a station is temporarily busy, movers can go to another station of the same type; when an area must be paused, the travel path can also beadjustedwithin the existing working plane. The way products flow can be reorganized according to equipment status.
Path flexibility must be designed together with process rules. Which stations can substitute for each other, which processes must be executed in sequence, and where abnormal products should go — all of this should be clarified at the equipment concept stage.The MagiFloater intelligent simulation and scheduling systemcan be used to configure the working plane, process stations and operating tasks, and to verify paths and cycle times before actual deployment.